TT tasks
Task |
Date |
Delegated |
Deadline |
Completed (by, date) |
Remarks |
Asking e-signature from HoC |
TT meeting August |
Zsolt |
ASAP |
Zsolt 4 Sep |
|
Invitation for PR Anna, Bus search training |
TT meeting August |
Agnes and Zsolt |
ASAP |
Zsolt 15 Sep |
|
Contacting FRONTEX regarding the Integrity training cooperation |
TT meeting August |
Agnes |
ASAP |
Agnes 4 Sep 19 Sep follow up reminder was sent |
|
Finalising the invitation for Integrity |
TT meeting August |
Zsolt, Anna, Immo, George |
ASAP |
Zsolt, Anna, Immo, George 8 Sep |
Ok (I.K) |
CLEP call for CCP training |
TT meeting August |
Zsolt |
ASAP |
Zsolt 8 Sep |
|
Planning training activities for the first half of 2024 |
TT meeting August |
All |
mid October |
|
|
Contacting PR Anna regarding the PR representatives participation on the trainings |
TT meeting August |
Zsolt |
mid Sep |
|
|
Info about the trainings for PR purposes (before-during-after) – discussion with PR Anna |
TT meeting August |
Zsolt |
mid Sep |
|
|
Official letter template for appreciation of the trainers |
TT meeting August |
Agnes |
mid Sep |
Agnes 8 Sep |
|
Collecting the missing info from CoE |
TT meeting August |
All |
mid Sep |
|
|
Reviewing the content of the CELBET courses |
TT meeting August |
All |
see above |
|
|
Preparing a template as a guide for trainers |
TT meeting August |
Zsolt |
mid September |
|
|
Migration of the courses |
TT meeting August |
All |
see above |
|
|
Updating the progress report |
TT meeting August |
Zsolt and All |
mid September |
Zsolt 20 Sep |
The 39 month report was sent to Pille (Z.D) |
e-mail about updating the info of NTCPs (deadline 20 Sep) |
TT meeting August |
Agnes |
ASAP |
Agnes 8 Sep |
|
follow up mail asking for updating or completing the table about the national training structure (deadline 10 Oct) |
TT meeting August |
Agnes |
25 Sep |
Agnes 26 Sep |
|
invitation for the on-line network meeting |
TT meeting August |
Agnes |
mid October |
|
|
Testing and finding the best solution for the database |
TT meeting August |
Immo and All |
mid September |
|
Ongoing |
Contacting the Team Leaders on the training needs on deliverables |
TT meeting August |
Zsolt |
mid September |
|
It will be discussed on the October MGT meeting |
The CoE application form need to be sent to Raluca |
TT meeting August |
Zsolt |
mid September |
|
|
Starting the preparation of the RA training program |
TT meeting August |
Zsolt |
mid September |
|
|
Contacting the trainers for ID |
TT meeting August |
Agnes |
ASAP |
Agnes 15th Sep deadline for collecting pics 20 Sep prolonged deadline |
All collected pictures were sent to PR Expert. |
|
|
||||
|
|
|
|
|
|
|
|
|
|
|